Power Generation

Karuma HPP(600MW): overall progress of the works stands at 74% complete.

 

Isimba HPP(183MW): overall progress of works stands at 79% and to be commissioned before end of 2018. 

 

Achwa/Agago HPP(83MW): Construction of the 41MW Achwa 2 is on going and will be commissioned in November 2018. RAP implementation is ongoing with the expectation of acquiring 50% of the corridor by July 2018. Overall progress of Achwa 1 is at 70%

 

Muzizi(48MW): Procuring the EPC Contractor is ongoing.

 

Nyagak III (6.6MW): Construction works on this project have stalled since KfW (a German Bank) withdraw a Euro 6M grant towards the project. 

 

GETFIT Portfolio (156.5MW): All projects under the GETFIT portfolio are currently under construction. For FY 2017/18, three projects (Lubilia 5.4MW, Rwimi 5.5MW, Tororo Solar 10MW) were all commissioned. More projects expected to be commissioned before end of 2018

Achievement image: 
Category: